Project Description:
SHARON- BRIDGE REHABILITATIONS, BR# S-09-011, S-09-010, S-09-009, ROUTE 1/ROUTE I-95
The purpose of this project is to replace the three bridge decks carrying Route 1 Northbound over I-95. For one of the bridges, the work also includes the demolition of the superstructure, excluding the steel beams, surface preparation and painting of all steel, as well as the construction of the new proposed deck.
Location:
  • Town of Sharon
  • Resident Engineer: Brian Lewis
    Construction Contract Value: $12,222,427.43
    Construction Bid Price: $7,842,302.00
    Initial Construction Estimate: $6,188,193.90
    District: District 5

    Contracts (1) Progress
    # 44232 -- Construction Contract
    Sharon - Bridge Deck Replacements (S-09-009, S09-010 and S-09-11) on Route 1 Northbound over Interstate 95 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/30/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/28/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 06/10/2002
    Project Status Advertised 08/20/2005
    Project Management
    25% Design 25% Package Received 08/15/2002
    25% Design 25% Package Comments to DE 05/12/2003
    75% Design 75% Package Received 01/19/2005
    75% Design 75% Package Comments to DE 05/20/2005
    Final Design PS&E Received 08/01/2005
    Final Design PS&E to FAPRO 08/05/2005
    Consultant Contract Process NTP Issued 04/04/2002