LUNENBURG- BRIDGE REPLACEMENT, BR# L-17-010, LEOMINSTER-SHIRLEY ROAD OVER THE B&M RR & MBTA
This project is essentially the replacement of the Leominster-Shirley Road Bridge over the B&M RR. The new bridge will have a three span steel supported deck structure with new abutments behind the existing abutments. A temporary bridge will be used to manage traffic while the existing bridge is under construction. The work includes full depth reconstruction of the roadways approaching the bridge, drainage system improvements, granite curb installation, cement concrete sidewalks, hot mix asphalt driveway construction, pavement markings and sign installation, and other necessary landscaping.
Location:
  • Town of Lunenburg
  • Resident Engineer: Frederick Stacy
    Construction Contract Value: $4,835,402.00
    Construction Bid Price: $4,335,820.00
    Initial Construction Estimate: $3,369,700.00
    District: District 3
    Current Status: Performing site clean-up and working on punch list items. (as of 07/17/2008)

    Contracts (4) Progress
    # 32181 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract N Final
    # 43179 -- Design -- Hwy Eng Open End
    Layout Section requires a consultant to provide the service of Layout plan and written description preparation. Final
    # 44339 -- Construction Contract
    Lunenburg - Bridge Replacement (L-17-010) Leominster/Shirley Road over the B&M & MBTA Railroad Completed
    # 57732 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects, includes ABP projects Final

    Bridges

    Contract Dates
    Notice to Proceed: 06/20/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Performing site clean-up and working on punch list items.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/11/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 06/10/2002
    Project Status Advertised 09/17/2005
    Project Management
    100% Design 100% Package Received 08/12/2005
    100% Design 100% Package Comments to DE 09/09/2005
    25% Design 25% Package Received 07/31/2003
    25% Design 25% Package Comments to DE 01/12/2004
    25% Design Design Public Hearing 03/08/2004
    75% Design 75% Package Received 06/18/2004
    75% Design 75% Package Comments to DE 03/16/2005
    Final Design PS&E Received 08/12/2005
    Final Design PS&E to FAPRO 08/19/2005
    Consultant Contract Process NTP Issued 03/04/2003