DISTRICT 4- SCHEDULED AND EMERGENCY STRUCTURAL REPAIRS AT VARIOUS LOCATIONS (NORFOLK & SUFFOLK) (3 SEPARATE CONTRACTS)
Location:
Resident Engineer: Brian Zilinsky
Construction Contract Value: $4,127,955.00
Construction Bid Price: $1,667,955.00
Initial Construction Estimate: $2,204,500.00
District: District 4
Current Status: Work under this contract consists of preparing structural repair designs and furnishing various artisans--- iron workers, mechanics, welders, carpenters, laborers---- and materials, supplies, equipment and engineering services to perform non-routine and emergency structural repairs. (as of 02/16/2005)
Additional Info: This contract is now complete. (as of 02/16/2006)

Contracts (1) Progress
# 33225 -- Construction Contract
Scheduled and Emergency Bridge Structural Repairs. NORFOLK & SUFFOLK COUNTIES (3 Separate Contracts) Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/03/2003
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Work under this contract consists of preparing structural repair designs and furnishing various artisans--- iron workers, mechanics, welders, carpenters, laborers---- and materials, supplies, equipment and engineering services to perform non-routine and emergency structural repairs.
    Additional Info
    This contract is now complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/20/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/14/2002
    Project Status Advertised 10/19/2002