TOWNSEND- BRIDGE REPLACEMENT, T-07-008, WHEELER ROAD OVER WILLARD BROOK
This project consists of replacing the current bridge with a new steel bridge to be built on the same alignment as the existing bridge. The proposed bridge will have a curb to curb dimension of 29.5 feet. A 5 foot sidewalk will be located on the north side of the bridge. During construction, the bridge will be closed and vehicular traffic will be detoured. A temporary sidewalk will be constructed to allow pedestrians to cross Willard Brook.
Location:
  • Town of Townsend
  • Resident Engineer: Frederick Stacy
    Construction Contract Value: $1,339,105.00
    Construction Bid Price: $1,198,605.00
    Initial Construction Estimate: $1,460,551.00
    District: District 3

    Contracts (3) Progress
    # 54830 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 63236 -- Construction Contract
    Bridge Replacement (T-07-008) (Steel) – Wheeler Road over Willard Brook. Completed
    # 96060 -- Design -- Bridge Open End
    RD 3 F/A NON-NHS BRIDGES-CON Q Final

    Bridges

    Contract Dates
    Notice to Proceed: 06/30/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/21/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Status Advertised 02/20/2010
    Project Management
    100% Design 100% Package Received 04/28/2009
    25% Design 25% Package Received 04/10/2003
    25% Design 25% Package Comments to DE 10/15/2004
    25% Design Design Public Hearing 07/18/2005
    75% Design 75% Package Received 01/23/2007
    75% Design 75% Package Comments to DE 01/10/2008
    Final Design PS&E Received 12/31/2009
    Final Design PS&E to FAPRO 02/11/2010
    Consultant Contract Process Scope to DE 09/04/2002
    Consultant Contract Process NTP Issued 11/26/2002