25% Design |
25% Package Received |
04/08/2010 |
25% Design |
25% Package Comments to DE |
05/14/2010 |
25% Design |
25% Package Comments to DE |
05/14/2010 |
25% Design |
25% Package Comments to DE |
05/14/2010 |
25% Design |
25% Package Comments to DE |
05/14/2010 |
25% Design |
25% Package Comments to DE |
05/14/2010 |
25% Design |
25% Package Comments to DE |
05/14/2010 |
25% Design |
25% Package Comments to DE |
05/14/2010 |
25% Design |
25% Package Comments to DE |
05/14/2010 |
25% Design |
25% Package Comments to DE |
05/14/2010 |
25% Design |
25% Package Comments to DE |
05/21/2010 |
25% Design |
25% Package Comments to DE |
05/24/2010 |
25% Design |
25% Package Comments to DE |
07/28/2010 |
25% Design |
Design Public Hearing |
08/04/2003 |
25% Design |
Design Public Hearing |
06/15/2010 |
75% Design |
75% Package Received |
11/02/2010 |
75% Design |
75% Package Comments to DE |
11/05/2010 |
75% Design |
75% Package Comments to DE |
11/08/2010 |
75% Design |
75% Package Comments to DE |
11/15/2010 |
75% Design |
75% Package Comments to DE |
11/19/2010 |
75% Design |
75% Package Comments to DE |
11/29/2010 |
75% Design |
75% Package Comments to DE |
01/29/2011 |
75% Design |
75% Package Comments to DE |
02/28/2011 |
Final Design |
PS&E Received |
03/09/2011 |
Final Design |
PS&E to FAPRO |
04/26/2011 |
Consultant Contract Process |
Scope to DE |
10/09/2009 |
Consultant Contract Process |
NTP Issued |
10/16/2009 |
Consultant Contract Process |
Workhours Approved |
11/04/2009 |