LANESBOROUGH- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE 7
The project begins at the Pittsfield/Lanesborough line and proceeds northerly to Mile Marker 36.95. It includes resurfacing the roadway and reconstructing some areas where the foundation has failed, removing and resetting granite curbing and improving drainage. Existing guard rail will be retained and existing buried ends will be replaced with end treatments suitable for high speed application.
Location:
  • Town of Lanesborough
  • Resident Engineer: John Pierce
    Construction Contract Value: $3,657,653.06
    Construction Bid Price: $2,815,000.00
    Initial Construction Estimate: $2,541,957.00
    District: District 1
    Current Status: The contractor is installing traffic signs. (as of 11/21/2007)

    Contracts (1) Progress
    # 43670 -- Construction Contract
    Work consist of resurfacing a section of Route 7 in the Town of Lanesborough. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/17/2006
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The contractor is installing traffic signs.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/29/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Status Advertised 09/03/2005
    Project Management
    75% Design 75% Plans Complete 05/25/2005
    Final Design PS&E Received 08/31/2005
    Final Design PS&E to FAPRO 08/31/2005