NORTHBOROUGH- BRIDGE REHABILITATION, BR# N-20-002, ALLEN STREET OVER THE ASSABET RIVER
The purpose of this project is to replace the superstructure of the Allen Street Bridge over Assabet River and includes the reconstruction of 50 feet of roadway approaches. Traffic will be detoured during the construction of this bridge project.
Location:
  • Town of Northborough
  • Resident Engineer: Michael Sholock
    Construction Contract Value: $947,045.00
    Construction Bid Price: $792,314.00
    Initial Construction Estimate: $481,147.50
    District: District 3

    Contracts (2) Progress
    # 44137 -- Construction Contract
    Northborough - Allen Street over the Assabet River, Bridge Replacement (Br. #N-20-002), Project File Number 603651 Completed
    # 77861 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 07/21/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/03/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/21/2002
    Project Status Advertised 08/20/2005
    Project Management
    100% Design 100% Package Received 02/08/2005
    100% Design 100% Package Comments to DE 04/13/2005
    25% Design 25% Package Received 12/11/2002
    25% Design 25% Package Comments to DE 01/13/2003
    75% Design 75% Package Received 07/29/2003
    75% Design 75% Package Comments to DE 08/12/2004
    Final Design PS&E Received 08/16/2005
    Final Design PS&E to FAPRO 08/16/2005