| Project Description: |
NORTHBOROUGH- BRIDGE REHABILITATION, BR# N-20-002, ALLEN STREET OVER THE ASSABET RIVER
The purpose of this project is to replace the superstructure of the Allen Street Bridge over Assabet River and includes the reconstruction of 50 feet of roadway approaches. Traffic will be detoured during the construction of this bridge project.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | Municipality |
| Project Manager: | Manhar Patel![]() |
| Estimated Total Contract Cost: | $947,045.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 3 |
| Current Status: | This project is in the preliminary design phase. |
|