Project Description:
LENOX- INTERSECTION IMPROVEMENTS, ROUTE 7 @ ROUTE 20
This project will include the realignment of the intersection from an "X" to a "T" type, installation of a new traffic signal and new pavement markings as well as warning, regulatory and directional signs within the project limits.
Location:
  • Town of Lenox
  • Resident Engineer: Thomas Viscuso
    Construction Contract Value: $2,740,187.50
    Construction Bid Price: $2,253,487.70
    Initial Construction Estimate: $1,906,430.00
    District: District 1
    Current Status: Construction is working on the edge of the roadway finishing up the project. (as of 06/06/2007)

    Contracts (1) Progress
    # 43288 -- Construction Contract
    Lenox - Roadway Reconstruction at the Intersection of Route 7 at Route 20 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/08/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Construction is working on the edge of the roadway finishing up the project.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/16/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/16/2002
    Project Status Advertised 06/11/2005
    Project Management
    100% Design 100% Package Received 12/16/2004
    100% Design 100% Package Comments to DE 01/07/2005
    25% Design 25% Package Received 01/06/2004
    25% Design Design Public Hearing 11/09/2004
    75% Design 75% Package Received 01/06/2004
    75% Design 75% Package Comments to DE 05/10/2004
    Final Design PS&E Received 05/23/2005
    Final Design PS&E to FAPRO 05/31/2005