RAYNHAM- INTERSECTION IMPROVEMENTS ON ROUTE 44 (CAPE HIGHWAY) AT CHURCH STREET
The work on this project includes installation of a fully actuated traffic signal system, along with new signs and pavement markings, new curbs and sidewalks. Also included is full depth reconstruction that includes the relocation of Leonard Street for better intersection alignment.
Location:
  • Town of Raynham
  • Design Responsibility: Municipality
    Right of Way Responsibility: MassDOT
    Project Manager: Andreina Luckett
    Estimated Total Federal Participating Construction Cost: $330,000.00
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 04/05/2003 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/16/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Status Advertised 04/05/2003
    Project Management