Project Description:
MAYNARD- BRIDGE REPLACEMENT, M-10-007, ROUTE 27 (WALTHAM STREET) OVER THE ASSABET RIVER
The proposed project will replace the bridge carrying Route 27 (Waltham Street) over the Assabet River. The proposed construction will include transitioning the approach roadway width to the proposed bridge width on the same alignments. Ornamental lighting on the bridge shall be restored and the utilities in the area shall be maintained. The bridge will remain open to traffic by using staged construction.
Location:
  • Town of Maynard
  • Resident Engineer: Thomas Lally
    Construction Contract Value: $3,826,708.00
    Construction Bid Price: $3,365,729.36
    Initial Construction Estimate: $3,512,722.50
    District: District 3

    Contracts (4) Progress
    # 30285 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 57462 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 67759 -- Construction Contract
    Bridge Replacement Br. No. M-10-007 (Steel) Route 27 (Waltham Street) over the Assabet River Completed
    # 77869 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/21/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/16/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 06/10/2002
    Project Status Advertised 09/11/2010
    Project Management
    100% Design 100% Package Received 08/25/2010
    25% Design 25% Package Received 04/05/2006
    25% Design 25% Package Comments to DE 03/02/2006
    25% Design Design Public Hearing 08/27/2008
    75% Design 75% Package Received 03/16/2010
    Final Design PS&E Received 08/25/2010
    Final Design PS&E to FAPRO 09/08/2010
    Consultant Contract Process NTP Issued 02/08/2010
    Consultant Contract Process Workhours Approved 02/01/2010