Project Description: |
BRIDGEWATER- TRAFFIC SIGNAL & INTERSECTION IMPROVEMENTS AT BROAD STREET (ROUTE 18) AND HIGH STREET
Work on this project consists of traffic signal upgrading and geometric improvements at the intersection of Broad Street (Route 18) and High Street.
|
Location: |
|
Resident Engineer: | Matthew Lambert |
Construction Contract Value: | $1,311,613.00 |
Construction Bid Price: | $1,119,547.00 |
Initial Construction Estimate: | $1,114,967.50 |
District: | District 5 |
|
Bridges |
|
|
|
|