Project Description: |
GREAT BARRINGTON- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE 7 & 23
This project will resurface Route 20 from the Belcher Square intersection to the Housatonic River Bridge. Sidewalks on both sides of the road will be replaced and upgraded to current ADA standards. Minor drainage improvements will be included along with new granite curb, cold planning and resurfacing.
|
Location: |
|
Resident Engineer: | Gary Liston |
Construction Contract Value: | $1,161,578.00 |
Construction Bid Price: | $1,006,593.00 |
Initial Construction Estimate: | $819,933.00 |
District: | District 1 |
|