Project Description:
MILFORD- UPPER CHARLES TRAIL CONSTRUCTION (TRANSPORTATION ENHANCEMENT PROJECT - PHASE I)
Phase 1 of Milford's segment of the proposed Upper Charles Trail (a 27-mile paved bike trail connecting the towns of Framingham, Sherborn, Holliston, Milford, Hopkinton, and Ashland) is approximately 3 miles long. It begins at two places, the Commuter Parking Lot on Main Street and the intersection of the existing railbed and Main Street. After these two legs of the trail meet, it runs northerly along the railbed over town land and under I-495 where it ends at Deer Street just north of Route I-495.
Location:
  • Town of Milford
  • Resident Engineer: Julio Fontecchio
    Construction Contract Value: $2,245,512.00
    Construction Bid Price: $1,464,102.50
    Initial Construction Estimate: $1,554,970.50
    District: District 3

    Contracts (1) Progress
    # 37664 -- Construction Contract
    Construction of the Upper Charles Trail Bikeway. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/14/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/30/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/21/2002
    Project Status Advertised 08/28/2004
    Project Management
    100% Design 100% Package Received 04/20/2004
    100% Design 100% Package Comments to DE 05/26/2004
    100% Design 100% Plans Complete 05/27/2004
    25% Design 25% Package Received 08/15/2002
    25% Design 25% Package Comments to DE 04/08/2003
    25% Design Design Public Hearing 10/29/2003
    25% Design 25% Plans Complete 04/08/2003
    75% Design 75% Package Received 08/27/2003
    75% Design 75% Package Comments to DE 11/21/2003
    75% Design 75% Plans Complete 11/21/2003
    Final Design PS&E Received 06/22/2004
    Final Design PS&E to FAPRO 07/12/2004