| Project Description:
|
DISTRICT 4- (MIDDLESEX & ESSEX COUNTIES) SCHEDULED AND EMERGENCY REPAIRS TO ABUTMENTS, PIERS AND COLUMNS (2 SEPARATE CONTRACTS)
|
| Location:
|
|
| Resident Engineer:
|
Robert Huettner |
| Construction Contract Value:
|
$3,192,042.00 |
| Construction Bid Price:
|
$2,052,042.00 |
| Initial Construction Estimate:
|
$2,254,815.00 |
| District:
|
District 4 |
| Current Status:
|
Work under this contract consists of removing deteriorated concrete from stem piers, pier caps and pier columns, walls and abutments and replacing excavated concrete and damaged reinforcing steel (as of 09/11/2008) |
| Additional Info:
|
This contract is now substansially complete. (as of 09/11/2008) |