Project Description:
AMESBURY- BRIDGE REPLACEMENT, A-07-026, ROUTE I-495 (NB & SB) OVER THE BIKEWAY (ABANDONED B&M RR LINE)
The existing I-495 westbound & eastbound bridges will be replaced by two precast arches. The openings underneath the precast arches will be as large as reasonably possible over the existing bikeway.
Location:
  • Town of Amesbury
  • Resident Engineer: Francis Welch
    Construction Bid Price: $6,515,258.00
    District: District 4

    Contracts (6) Progress
    # 30272 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 71613 -- Design -- Bridge Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for bridge, traffic and utility permit structural design and analysis assignments. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 90407 -- Construction Contract
    Bridge Replacement Br. No. A-07-026 (Precast Concrete Arch) Interstate 495 (NB&SB) over Amesbury Riverwalk Bikeway. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/30/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/20/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/12/2002
    Project Status Advertised 08/29/2015
    Project Management
    100% Design 100% Package Received 07/13/2015
    25% Design 25% Package Received 02/24/2015
    25% Design 25% Package Comments to DE 11/06/2014
    25% Design 25% Package Comments to DE 03/11/2015
    25% Design Design Public Hearing 03/19/2015
    75% Design 75% Package Received 04/23/2015
    Final Design PS&E Received 08/21/2015
    Final Design PS&E to FAPRO 08/25/2015
    Consultant Contract Process Scope to DE 08/15/2003
    Consultant Contract Process NTP Issued 12/30/2003