Project Description:
DISTRICT 3- SCHEDULED AND EMERGENCY STRUCTURAL REPAIRS AT VARIOUS LOCATIONS
The work to be done under this contract consists of preparing structural repair designs and furnishing various artisans (skilled laborers, carpenters, welders/iron workers, equipment operators) materials, supplies and equipment to perform non-routine structural maintenance and emergency repairs to structures throughout District Three.
Location:
Resident Engineer: James Robida
Construction Contract Value: $2,743,480.00
Construction Bid Price: $744,480.00
Initial Construction Estimate: $847,575.00
District: District 3
Current Status: Structural steel repairs are being performed on I-290 over Southbridge Street. No traffic delays are expected to occur. (as of 01/26/2005)

Contracts (1) Progress
# 33277 -- Construction Contract
Scheduled and Emergency Bridge Repairs at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/13/2003
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Structural steel repairs are being performed on I-290 over Southbridge Street. No traffic delays are expected to occur.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/28/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/18/2002
    Project Status Advertised 02/22/2003
    Project Management