Project Description:
CHATHAM- BRIDGE REPLACEMENT, C-07-001, BRIDGE STREET OVER THE MITCHELL RIVER
The purpose of the project is to remedy the bridge’s structural deficiencies and functional obsolescence, while keeping with the context of the surrounding area and accommodating all existing and future uses of the bridge. The current alternative consists of an all timber superstructure (including the wearing surface, structural deck, beams, sidewalks, and railings) with the exception of the bascule leaf which will consist of a steel frame. The superstructure would be supported on pile bent substructure units constructed with concrete-filled steel piles and concrete caps. The bascule span superstructure consists of a timber roadway deck and sidewalks on steel open grid flooring panels on the concrete bascule pier substructure. Additional improvements include transitioning and resurfacing of the approach roadways. The navigable channel will also be shifted 5 feet to the west and widened to provide 25 feet of horizontal clearance, fender to fender. Vehicular and pedestrian traffic will be detoured during construction.
Location:
  • Town of Chatham
  • Resident Engineer: Michael King
    Construction Contract Value: $15,298,630.50
    Construction Bid Price: $13,894,006.50
    Initial Construction Estimate: $12,929,072.63
    District: District 5

    Contracts (6) Progress
    # 32173 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract F Final
    # 57466 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 64311 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69764 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77886 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 80370 -- Construction Contract
    Bridge Replacement (C-07-001) (Single Leaf Bascule) Bridge Street over the Mitchell River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/28/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/03/2002
    Project Review Committee PRC Tabled 11/04/2002
    Project Review Committee PRC Approved 09/14/2006
    Project Status Initiated 09/18/2006
    Project Status Advertised 10/26/2013
    Project Management
    100% Design 100% Package Received 09/09/2013
    25% Design 25% Package Received 07/27/2012
    25% Design 25% Package Comments to DE 02/19/2010
    25% Design Design Public Hearing 03/18/2010
    75% Design 75% Package Received 04/24/2013
    75% Design 75% Plans Complete 07/16/2013
    75% Design 75% Plans Complete 07/18/2013
    Final Design PS&E Received 04/10/2014
    Final Design PS&E to FAPRO 09/25/2013
    Consultant Contract Process Scope to DE 01/22/2009
    Consultant Contract Process NTP Issued 07/29/2009