Project Description: |
FRAMINGHAM- BRIDGE RECONSTRUCTION, F-07-063, DANFORTH STREET OVER THE SUDBURY RIVER
This project proposes to replace the existing superstructure on the Danforth Street bridge over the Sudbury River with a two-span continuous superstructure. The superstructure shall be replaced with hot-dip galvanized steel stringers. The bridge will be closed during construction and a detour will be established.
|
Location: |
|
Resident Engineer: | Alan Webb |
Construction Contract Value: | $1,847,852.00 |
Construction Bid Price: | $1,590,741.00 |
Initial Construction Estimate: | $2,359,245.00 |
District: | District 3 |
|