DISTRICT 4- SIDEWALK REPAIR AND REHABILITATION AT VARIOUS LOCATIONS
The work consists of excavation and replacement of asphalt and cement sidewalks, removing and resetting curb and installation of new granite curb.
Location:
Resident Engineer: Walter Ulwick
Construction Contract Value: $470,125.50
Construction Bid Price: $405,375.50
Initial Construction Estimate: $428,600.00
District: District 4
Current Status: Work completed through Estimate # 8 , R & R curb reconstruction, Rte 3A , Billerica and Lexington. Contract completed as of 5/20/2006. (as of 06/21/2006)
Additional Info: This was the R.E.'S last estimate. (as of 06/21/2006)

Contracts (1) Progress
# 34609 -- Construction Contract
Sidewalk Repair and Rehabilitation at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/13/2004
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Work completed through Estimate # 8 , R & R curb reconstruction, Rte 3A , Billerica and Lexington. Contract completed as of 5/20/2006.
    Additional Info
    This was the R.E.'S last estimate.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/06/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/18/2002
    Project Status Advertised 02/07/2004