Project Description:
LEE- BRIDGE REPLACEMENT, L-05-023, OLD PLEASANT STREET OVER HOUSATONIC RIVER
The work under this project consists of the replacement of the Old Pleasant Street Bridge over the Housatonic River. The proposed structure will be a single-span pre-stressed concrete box beam superstructure with a hot mix asphalt deck surface. The new abutments will be constructed behind the existing abutments. The bridge profile shall meet the approach roadway profile. The width of the roadway shall meet the proposed approach roadway curb-to-curb width and a handicap accessible sidewalk will remain on the south side of the bridge. The bridge will be closed during construction and a detour route will be established. The utilities on the bridge structure will need to be relocated within the new structure.
Location:
  • Town of Lee
  • Resident Engineer: Joseph Mancari
    Construction Contract Value: $2,642,622.68
    Construction Bid Price: $2,375,363.00
    Initial Construction Estimate: $3,562,930.00
    District: District 1

    Contracts (2) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 60371 -- Construction Contract
    Bridge Replacement (L-05-023) (Concrete) - Old Pleasant Street over the Housatonic River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/08/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/19/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/12/2002
    Project Status Advertised 08/29/2009
    Project Management
    100% Design 100% Package Received 11/19/2007
    100% Design 100% Package Comments to DE 09/03/2008
    25% Design 25% Package Received 07/22/2003
    25% Design 25% Package Comments to DE 01/07/2004
    25% Design Design Public Hearing 07/21/2004
    75% Design 75% Package Received 12/21/2006
    75% Design 75% Package Comments to DE 05/11/2007
    Final Design PS&E Received 12/05/2008
    Final Design PS&E Received 07/16/2009
    Final Design PS&E to FAPRO 08/19/2009
    Consultant Contract Process Scope to DE 07/24/2002
    Consultant Contract Process NTP Issued 11/22/2002