Project Description:
CHELMSFORD- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE I-495
This project will result in a resurfaced I-495 from the Westford/Chelmsford town line to Exit 35 in Chelmsford. This project is 3.8 miles in length.
Location:
  • Town of Chelmsford
  • Resident Engineer: James Slavit
    Construction Contract Value: $4,479,297.00
    Construction Bid Price: $4,043,708.50
    Initial Construction Estimate: $3,981,785.00
    District: District 4
    Current Status: Job physically completed. (as of 08/26/2008)

    Contracts (1) Progress
    # 34060 -- Construction Contract
    Resurfacing and Related Work on a Section of Interstate 495. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/08/2004
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Job physically completed.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/19/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/12/2002
    Project Status Advertised 07/12/2003
    Project Management