Project Description:
WESTMINSTER- BRIDGE REPLACEMENT, W-28-007, ROUTE 12 (ASHBURNHAM STREET) OVER PHILLIPS BROOK
The proposed project consists of construction of a replacement bridge for State Route 12 (Ashburnham Street) Bridge over Phillips Brook. The proposed bridge will be a single span structure placed on a new abutments. The existing abutments will remain in place. In addition, the proposed project will include new bridge rail, drainage improvements, safety signing, pavement markings, and other incidental work. A temporary traffic signal will be used to control single lane travel over the bridge during construction.
Location:
  • Town of Westminster
  • Resident Engineer: Lisa Spezzaferro-Pelleti
    Construction Contract Value: $2,617,552.00
    Construction Bid Price: $2,248,820.00
    Initial Construction Estimate: $2,281,672.50
    District: District 3

    Contracts (2) Progress
    # 32180 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract M Final
    # 58047 -- Construction Contract
    Bridge Replacement (W-28-007) (Concrete) Route 12 (Ashburnham Road) over Phillips Brook Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/28/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/10/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/14/2002
    Project Status Advertised 12/06/2008
    Project Management
    100% Design 100% Package Received 08/20/2006
    100% Design 100% Package Comments to DE 01/08/2007
    25% Design 25% Package Received 07/21/2003
    25% Design 25% Package Comments to DE 11/28/2003
    25% Design Design Public Hearing 10/14/2004
    75% Design 75% Package Received 12/07/2005
    75% Design 75% Package Comments to DE 03/16/2006
    Final Design PS&E Received 07/21/2008
    Final Design PS&E to FAPRO 11/03/2008
    Consultant Contract Process NTP Issued 05/16/2003