Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DALTON- BRIDGE REPLACEMENT, D-01-012, CLEVELAND ROAD OVER WAHCONAH FALLS BROOK
The proposed project consists of the replacement of the existing bridge carrying Cleveland Road over Wahconah Fall Brook with a single span concrete superstructure. The curb to curb width shall be 26 feet with one 5.5 foot sidewalk on the west side. The bridge will be closed to both vehicular and pedestrian traffic and a detour will be provided.
Location:
  • Town of Dalton
  • Resident Engineer: Peter Lamarre
    Construction Contract Value: $940,605.80
    Construction Bid Price: $798,998.00
    Initial Construction Estimate: $1,280,112.00
    District: District 1

    Contracts (6) Progress
    # 32177 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract J Final
    # 37137 -- Design -- Footprint Bridge contracts
    (Footprint 6) Perform design on deficient State and/or municipally owned bridges as part of the Bridge Rehabilitation/Replacement/Preservation Program. Final
    # 57463 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 57465 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 68164 -- Construction Contract
    Bridge Replacement (D-01-012) (Concrete) - Cleveland Road over Wahconah Falls Brook (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/15/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/10/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/12/2002
    Project Status Advertised 01/15/2011
    Project Management
    100% Design 100% Package Comments to DE 09/09/2010
    100% Design 100% Package Comments to DE 09/10/2010
    100% Design 100% Package Comments to DE 09/13/2010
    100% Design 100% Package Comments to DE 09/24/2010
    100% Design 100% Package Comments to DE 10/04/2010
    25% Design 25% Package Received 03/13/2009
    25% Design 25% Package Comments to DE 08/27/2009
    25% Design 25% Package Comments to DE 03/26/2010
    25% Design 25% Package Approved 09/21/2009
    25% Design Design Public Hearing 10/28/2009
    25% Design 25% Plans Complete 09/15/2009
    75% Design 75% Package Received 05/03/2010
    75% Design 75% Package Comments to DE 05/26/2010
    75% Design 75% Package Comments to DE 06/14/2010
    75% Design 75% Package Comments to DE 06/16/2010
    75% Design 75% Package Comments to DE 06/18/2010
    75% Design 75% Package Comments to DE 08/02/2010
    Final Design PS&E Received 09/03/2010
    Final Design PS&E Received 01/07/2011
    Final Design PS&E to FAPRO 01/11/2011
    Consultant Contract Process Scope to DE 09/26/2008
    Consultant Contract Process NTP Issued 12/15/2008