CHARLEMONT- BRIDGE REPLACEMENT, C-05-036, MOUNTAIN ROAD OVER HARTWELL BROOK
The purpose of this project is to replace the structurally deficient bridge carrying Mountain Road over Hartwell Brook and its approach roadways in Charlemont.
Location:
  • Town of Charlemont
  • Resident Engineer: Hugo Pacheco
    Construction Contract Value: $1,081,077.40
    Construction Bid Price: $891,372.60
    Initial Construction Estimate: $1,113,098.00
    District: District 1

    Contracts (3) Progress
    # 32169 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract B Final
    # 59588 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 70090 -- Construction Contract
    Bridge Replacement (C-05-036) (Concrete) - Mountain Road over Hartwell Brook. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/13/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/17/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 01/06/2003
    Project Status Advertised 07/23/2011
    Project Management
    25% Design 25% Package Received 06/28/2006
    25% Design 25% Package Comments to DE 02/18/2010
    25% Design 25% Package Comments to DE 02/18/2010
    25% Design 25% Package Comments to DE 03/31/2010
    25% Design 25% Package Comments to DE 04/20/2010
    25% Design 25% Package Comments to DE 05/11/2010
    25% Design 25% Package Approved 02/14/2008
    25% Design Design Public Hearing 05/27/2010
    25% Design Design Public Hearing 05/27/2010
    25% Design 25% Plans Complete 06/28/2006
    75% Design 75% Package Received 01/07/2011
    75% Design 75% Package Comments to DE 01/14/2011
    75% Design 75% Package Comments to DE 01/18/2011
    75% Design 75% Package Comments to DE 02/04/2011
    75% Design 75% Package Comments to DE 02/10/2011
    75% Design 75% Package Comments to DE 02/11/2011
    75% Design 75% Plans Approved 03/04/2011
    75% Design 75% Plans Complete 02/04/2011
    Final Design PS&E Received 04/21/2011
    Final Design PS&E to FAPRO 07/19/2011
    Consultant Contract Process Scope to DE 02/25/2005
    Consultant Contract Process NTP Issued 12/29/2005
    Consultant Contract Process Workhours Approved 12/29/2005