Project Description:
BRIMFIELD- PALMER- BRIDGE REPLACEMENT, B-24-012=P-01-011, KING'S BRIDGE OVER QUABOAG RIVER
This is a bridge replacement project including substructure and superstructure. The scope calls for the widening of the structure to provide an 26.2 foot roadway. The overall extent of the widening is 6.2 feet. No sidewalk is planned. The roadway profile will closely match the existing, as will the hydraulic opening. The roadway widening and slope stabilization can be accomplished by adding to the embankment and by the placing of slope stabilization materials. The superstructure design will incorporate provisions for future utilities.
Location:
  • Town of Brimfield
  • Town of Palmer
  • Resident Engineer: Mark Shea
    Construction Contract Value: $1,741,318.00
    Construction Bid Price: $1,568,017.00
    Initial Construction Estimate: $2,330,765.15
    District: District 2

    Contracts (4) Progress
    # 32171 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract D Final
    # 54837 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57730 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 67019 -- Construction Contract
    Bridge Replacement (B-24-012=P-01-011) (Steel) – King’s Bridge Road over the Quaboag River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/19/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/16/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/12/2002
    Project Status Advertised 09/04/2010
    Project Management
    100% Design 100% Package Received 04/27/2010
    100% Design 100% Package Comments to DE 06/10/2010
    25% Design 25% Package Received 05/01/2007
    25% Design 25% Package Comments to DE 09/21/2007
    25% Design Design Public Hearing 09/16/2008
    75% Design 75% Package Received 09/19/2008
    75% Design 75% Package Comments to DE 11/20/2008
    Final Design PS&E Received 08/16/2010
    Final Design PS&E to FAPRO 08/31/2010
    Consultant Contract Process NTP Issued 07/11/2008