Project Description:
AMHERST- HADLEY- SUNDERLAND- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE 116
The project begins after the divided section of Route 116 in Hadley and extends northward along Route 116 to just south of North Silver Lane in Sunderland. The work to be done consists of coldplaning and resurfacing; rebuilding and adjusting drainage structures; tree trimming; guardrail repair; and signage.
Location:
  • Town of Amherst
  • Town of Hadley
  • Town of Sunderland
  • Resident Engineer: Joseph Gaudet Jr
    Construction Contract Value: $1,610,898.24
    Construction Bid Price: $1,431,382.00
    Initial Construction Estimate: $1,375,500.00
    District: District 2
    Current Status: Physical work completed. (as of 07/27/2006)

    Contracts (1) Progress
    # 37540 -- Construction Contract
    Work consist of Hot Mix Asphalt excavation by cold planer, rebuilding and adjusting drainage structures, replacing pavement markings. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/22/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Physical work completed.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/23/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/12/2002
    Project Status Advertised 09/25/2004
    Project Management
    Final Design PS&E Received 07/07/2004
    Final Design PS&E to FAPRO 07/07/2004