FRAMINGHAM- BRIDGE REPLACEMENT, F-07-015, WINTER STREET OVER MBTA, AMTRAK & CSX RAILROAD
The proposed project will replace the existing structurally deficient, functionally obsolete bridge carrying Winter Street over the MBTA, Amtrak and CSX railroads.. The proposed abutments will be located behind the existing abutments to increase the number of railroad tracks beneath the bridge. If feasible, the proposed bridge will be widened to accommodate an additional turning lane in each direction.
Location:
  • Town of Framingham
  • Resident Engineer: Neil Ahearn
    Construction Contract Value: $7,849,999.00
    Construction Bid Price: $6,649,130.00
    Initial Construction Estimate: $7,751,418.00
    District: District 3

    Contracts (6) Progress
    # 58996 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 59554 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 64300 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64311 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77852 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 79396 -- Construction Contract
    Bridge Replacement (F-07-015) (Steel) Winter Street over the MBTA Railroad. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/28/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/23/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/12/2002
    Project Status Advertised 08/24/2013
    Project Management
    25% Design 25% Package Received 12/23/2011
    25% Design 25% Package Comments to DE 03/04/2011
    25% Design 25% Package Approved 02/15/2011
    25% Design Design Public Hearing 07/26/2012
    75% Design 75% Package Received 10/22/2012
    Final Design PS&E Received 06/18/2013
    Final Design PS&E to FAPRO 08/21/2013
    Consultant Contract Process Scope to DE 02/11/2010
    Consultant Contract Process NTP Issued 04/20/2010