Project Description:
NEEDHAM- WELLESLEY- 6 BRIDGE LOCATIONS ON I-95/ROUTE 128: N-04-020, N-04-021, N-04-022, N-04-026, N-04-027, N-04-037 & W-13-023 (ADD-A-LANE - CONTRACT V)
This project is the final bridge contract (Bridge V) for the I-95/93 (Route 128) Transportation Improvement Project. The work includes six bridge locations and approximately 3.25 miles of I-95 roadway reconstruction. The roadway work on I-95, from just south of Kendrick Street to just north of Route 9, includes the installation of an additional 12 foot travel lane and 10 foot shoulder in each direction toward the median, along with new collector/distributor roads between Highland Avenue and Kendrick Street. The collector roads will provide safer weaving movements between the interchanges and provide safer traffic movements to and from the adjacent business park. The bridge locations include the following: Kendrick Street over I-95 (Route 128) in Needham; Highland Avenue over I-95 (Route 128) in Needham; MBTA RR (Newton Upper Falls Branch) over I-95 (Route 128) in Needham (BRIDGE REMOVAL); I-95 (Route 128) over Central Street in Needham; Ramp K-1 Bridge over CD Road, and I-95 (Route 128) over Route 9 in Wellesley.
Location:
  • Town of Needham
  • Town of Wellesley
  • Construction Begins: Autumn 2014
    Resident Engineer: -- not assigned --
    Construction Contract Value: $185,192,026.16
    Construction Bid Price: $137,590,000.00
    Initial Construction Estimate: $135,117,702.00
    District: District 6

    Contracts (13) Progress
    # 115769 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 34072 -- Design -- Bridge Rehab/Recon/New Const
    Needham/Wellesley - Design for the replacement/rehabilitation of bridges under the final bridge contract of the I-95/93 Route 128 Transportation Improvement Project. Final
    # 57735 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 62936 -- Non-system contract type
    Statewide-Owner's Representative-Will perform peer reviews and manage cost recovery and value engineering on various projects.
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64317 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 65756 -- Design -- Geotechnical
    Work will consist of Geotechnical Review during the design of bridge structures and/or roadways owned by MassDOT and Cities and Towns throughout the Commonwealth. Final
    # 68387 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 76262 -- Non-system contract type
    Perform various assignments as the Owner's Representative for the peer review of engineering elements associated with satewide construction projects.
    # 77866 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77875 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 79875 -- Construction Contract
    Add-A-Lane Contract V along a Section of Interstate 95 Includes 6 Bridges. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/17/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/26/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/25/2002
    Project Status Advertised 09/21/2013
    Project Management
    100% Design 100% Package Received 05/03/2013
    100% Design 100% Package Comments to DE 08/06/2013
    25% Design 25% Package Received 12/11/2008
    25% Design 25% Package Received 09/02/2010
    25% Design 25% Package Comments to DE 11/08/2010
    25% Design 25% Package Comments to DE 11/08/2010
    25% Design 25% Package Comments to DE 10/27/2011
    25% Design 25% Package Comments to DE 04/23/2012
    25% Design 25% Package Comments to DE 04/30/2012
    25% Design Design Public Hearing 06/01/2011
    75% Design 75% Package Received 03/30/2012
    75% Design 75% Package Received 04/09/2013
    75% Design 75% Package Comments to DE 10/26/2012
    Final Design PS&E Received 09/10/2013
    Final Design PS&E Received 11/15/2013
    Final Design PS&E Received 01/23/2014
    Final Design PS&E to FAPRO 09/11/2013
    Consultant Contract Process Scope to DE 03/21/2005
    Consultant Contract Process NTP Issued 10/13/2006
    Consultant Contract Process Workhours Approved 02/06/2006