GRAFTON- SIGNAL & INTERSECTION IMPROVEMENTS @ ROUTE 122 AND MILLBURY STREET
This project will enhance safety and improve efficiency by installing a new traffic signal at the intersection of Providence Road (Route 122) and Millbury Street in Grafton. There will also be other improvements at this intersection, such as road widening and geometric improvements to accommodate improved lane configurations, along with minor drainage improvements and the installation of new signs and pavement markings.
Location:
  • Town of Grafton
  • Design Responsibility: Municipality
    Right of Way Responsibility: MassDOT
    Project Manager: Brian Chapman
    Estimated Total Contract Cost: $934,906.12
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information