| Project Description: |
DOVER- NEEDHAM- BRIDGE REPLACEMENT, D-10-004=N-04-007, WILLOW STREET OVER CHARLES RIVER
The work includes the replacement of the Willow Street bridge over the Charles River. The bridge will be closed and a traffic detour is required.
|
| Location: |
|
| Resident Engineer: | Daniel Stiven![]() |
| Construction Contract Value: | $3,356,767.00 |
| Construction Bid Price: | $2,864,546.00 |
| Initial Construction Estimate: | $3,636,379.10 |
| District: | District 6 |
|