DANVERS- BRIDGE REPLACEMENT, D-03-026, ROUTE 1 OVER CENTRE STREET (NB & SB)
The proposed project consists of the replacement of the existing bridges and abutments for the Route One Northbound and Southbound structures over Centre Street, and includes improvements to the interchange ramp terminals and speed change lanes. The proposed replacement bridges will consist of a reinforced concrete deck slab supported on 3-span continuous beams. The new substructures will consist of concrete abutments and drilled shaft piers. Also included will be new bridge rail, highway guard rail, median barrier, pavement markings, signs, and hot mix asphalt. The proposed work will be constructed within the existing highway layout.
Location:
  • Town of Danvers
  • Resident Engineer: Bernard LaVita
    Construction Contract Value: $5,747,550.00
    Construction Bid Price: $4,982,500.15
    Initial Construction Estimate: $8,097,809.00
    District: District 4

    Contracts (1) Progress
    # 60195 -- Construction Contract
    Bridge Replacement (D-3-26) (Steel) - Route 1 (NB & SB) (Newbury Street) over Center Street. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/28/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/07/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/14/2002
    Project Status Advertised 08/08/2009
    Project Management
    100% Design 100% Package Received 12/08/2008
    100% Design 100% Package Comments to DE 04/28/2009
    25% Design 25% Package Received 01/09/2004
    25% Design 25% Package Comments to DE 08/16/2004
    25% Design Design Public Hearing 10/20/2005
    75% Design 75% Package Received 07/08/2006
    75% Design 75% Package Comments to DE 10/03/2008
    Final Design PS&E Received 06/18/2009
    Final Design PS&E to FAPRO 07/31/2009
    Consultant Contract Process Scope to DE 12/30/2002
    Consultant Contract Process NTP Issued 07/16/2003