Project Description:
LAWRENCE- BRIDGE REHABILITATION, L-04-014, EAST HAVERHILL STREET OVER THE SPICKET RIVER
The work for this project consists of replacing the East Haverhill Street Bridge over the Spicket River with a single span cast in place reinforced concrete deck structure with an asphalt riding surface. The bridge will have a handicap accessible sidewalk on both sides and new bridge rail. The curb to curb width of the bridge will meet the approach roadways. The new substructure will be constructed behind the existing substructure. The bridge will be constructed in phases maintaining a single lane of traffic in one direction.
Location:
  • City of Lawrence
  • Resident Engineer: William Murphy
    Construction Contract Value: $3,136,646.00
    Construction Bid Price: $2,312,348.00
    Initial Construction Estimate: $3,478,810.00
    District: District 4

    Contracts (5) Progress
    # 32165 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract A Final
    # 43179 -- Design -- Hwy Eng Open End
    Layout Section requires a consultant to provide the service of Layout plan and written description preparation. Final
    # 54829 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review servicesto MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 58733 -- Construction Contract
    Bridge Replacement (L-04-014) (Concrete) - East Haverhill Street over the Spicket River. Completed
    # 64301 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 07/30/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/19/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/14/2002
    Project Status Advertised 04/11/2009
    Project Management
    100% Design 100% Package Received 05/12/2006
    100% Design 100% Package Comments to DE 07/11/2006
    100% Design 100% Plans Approved 08/15/2008
    25% Design 25% Package Received 12/22/2003
    25% Design 25% Package Comments to DE 12/03/2004
    25% Design Design Public Hearing 12/06/2004
    75% Design 75% Package Received 09/09/2005
    75% Design 75% Package Comments to DE 12/27/2005
    Final Design PS&E Received 02/17/2009
    Final Design PS&E to FAPRO 04/08/2009
    Consultant Contract Process Scope to DE 09/24/2002
    Consultant Contract Process NTP Issued 01/31/2003