Project Description:
PRINCETON- BRIDGE REPLACEMENT, P-16-014, ROUTE 62 (HUBBARDSTON ROAD) OVER WARE RIVER
The work under this project consists of the replacement of the Route 62 (Hubbardston Road) Bridge over the Ware River (East Branch). The work will include complete replacement of the deck structure and construction of new abutments behind the existing abutments. The new bridge will be a single-span structure consisting of a concrete deck supported by precast concrete deck beams. The work will also include full-depth roadway reconstruction along the approaches to the bridge for a total length of approximately 520 feet. A temporary bridge will be constructed adjacent to the existing bridge on the south side. The temporary bridge will provide one lane of traffic controlled by a traffic signal throughout the duration of construction.
Location:
  • Town of Princeton
  • Resident Engineer: Lisa Spezzaferro-Pelleti
    Construction Contract Value: $1,130,900.00
    Construction Bid Price: $1,085,000.00
    Initial Construction Estimate: $1,488,835.00
    District: District 3
    Current Status: Binder course has been placed on the bridge and roadway.The temporary bridge has been demolished. Traffic was switched to the new bridge, but remains alternating one-way under the temporary traffic signals. (as of 11/10/2008)

    Contracts (2) Progress
    # 30284 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 51611 -- Construction Contract
    Princeton - Bridge Replacement (P-16-14) Route 62 (Hubbardston Road) over the East Branch of the Ware River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 09/21/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Binder course has been placed on the bridge and roadway.The temporary bridge has been demolished. Traffic was switched to the new bridge, but remains alternating one-way under the temporary traffic signals.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/27/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/14/2002
    Project Status Advertised 07/29/2006
    Project Management
    100% Design 100% Package Received 07/05/2005
    100% Design 100% Package Comments to DE 08/09/2005
    25% Design 25% Package Received 05/13/2003
    25% Design 25% Package Comments to DE 12/12/2003
    25% Design Design Public Hearing 03/29/2004
    75% Design 75% Package Received 07/20/2004
    75% Design 75% Package Comments to DE 06/22/2005
    Final Design PS&E Received 05/05/2006
    Final Design PS&E to FAPRO 05/23/2006
    Consultant Contract Process NTP Issued 01/31/2003