Project Description:
LEXINGTON- BRIDGE REPLACEMENT, L-10-010, ROUTE 2A (MARRETT ROAD) OVER I-95/ROUTE 128
The existing bridge will be replaced in the same alignment with improvements made to the approach roadways and the interchange ramps.
Location:
  • Town of Lexington
  • Construction Begins: Spring 2023
    Resident Engineer: Timothy Manhardt
    Construction Bid Price: $26,119,931.00
    District: District 4

    Contracts (6) Progress
    # 121393 -- Construction Contract
    Bridge Replacement and Related Work (Including Signals and Roundabout Construction) Br. No. L-10-010 (Steel) Route 2A (Marrett Road) over Interstate 95 48% Complete
    # 32184 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract Q Final
    # 57598 -- Design -- Hwy Eng Open End
    Work will consist of providing design and engineering services to MassHighway on a task order basis for various statewide Value Engineering Studies. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64318 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 05/22/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/30/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/25/2002
    Project Status Advertised 02/11/2023
    Project Management
    100% Design 100% Package Received 06/30/2022
    25% Design 25% Package Received 06/15/2006
    25% Design 25% Package Received 01/01/2016
    25% Design 25% Package Comments to DE 07/24/2008
    25% Design Design Public Hearing 07/17/2008
    75% Design 75% Package Received 09/21/2009
    Final Design PS&E Received 09/22/2022
    Final Design PS&E Received - Resub 1 01/10/2023
    Consultant Contract Process Scope to DE 12/30/2002
    Consultant Contract Process NTP Issued 05/14/2003
    Consultant Contract Process Workhours Approved 05/02/2003