Project Description:
LOWELL- BRIDGE REPLACEMENT, L-15-072, LOWELL CONNECTOR (EB & WB) OVER PLAIN STREET
This proposed project will replace both the eastbound and westbound bridges of the Lowell Connector over Plain Street, improve the interchange ramps, and provide for future traffic signals at the intersections of the ramps with Plain Street. The Lowell Connector and Plain Street traffic will not be interrupted during construction by implementing a traffic management plan with multiple construction phases.
Location:
  • City of Lowell
  • Resident Engineer: Anthony Neve
    Construction Contract Value: $6,895,811.15
    Construction Bid Price: $6,963,321.25
    Initial Construction Estimate: $9,446,016.00
    District: District 4

    Contracts (3) Progress
    # 32176 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract I Final
    # 57465 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 66461 -- Construction Contract
    Bridge Replacement (L-15-072) (Steel) - Lowell Connector (EB and WB) over Plain Street Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/16/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/06/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/14/2002
    Project Status Advertised 07/24/2010
    Project Management
    100% Design 100% Package Received 07/10/2009
    100% Design 100% Package Comments to DE 07/21/2009
    100% Design 100% Package Comments to DE 05/25/2010
    25% Design 25% Package Received 07/12/2004
    25% Design 25% Package Comments to DE 08/29/2005
    25% Design Design Public Hearing 05/18/2006
    75% Design 75% Package Received 05/23/2007
    75% Design 75% Package Comments to DE 03/03/2009
    Final Design PS&E Received 07/01/2010
    Final Design PS&E to FAPRO 07/21/2010
    Consultant Contract Process Scope to DE 06/27/2003
    Consultant Contract Process NTP Issued 10/03/2003