COLRAIN- BRIDGE REHABILITATION, BR# C-18-003, LYONSVILLE ROAD OVER THE NORTH RIVER
This project involves the rehabilitation of the historic Arthur A. Smith covered bridge which has been removed from its original location. It will be rehabilitated and reinstalled in its original location on Lyonsville Road over the East Branch of the North River.
Location:
  • Town of Colrain
  • Resident Engineer: Charles Najimy
    Construction Contract Value: $2,344,729.00
    Construction Bid Price: $2,096,117.50
    Initial Construction Estimate: $1,427,971.00
    District: District 1
    Current Status: The guardrail is beng installed which will complete the project. (as of 05/14/2007)

    Contracts (2) Progress
    # 32173 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract F Final
    # 42088 -- Construction Contract
    Colrain - Lynonville Rd Br. # C-18-3 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/29/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    Municipally sponsored design
    This project began as Town designed project. After multiple revisions, MassHighway agreed to select a design consultant to complete the design from the 100% stage and advertise the project for construction.
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The guardrail is beng installed which will complete the project.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/23/2002
    Project Review Committee PRC Tabled 11/04/2002
    Project Review Committee PRC Approved 04/14/2003
    Project Status Advertised 04/02/2005
    Project Management
    100% Design 100% Package Received 03/25/2003
    100% Design 100% Package Comments to DE 09/02/2004
    Final Design PS&E Received 03/08/2005
    Final Design PS&E to FAPRO 03/08/2005