Project Description:
NORTHAMPTON- BRIDGE REPLACEMENT, N-19-029, RIVER ROAD OVER THE MILL RIVER
The proposed River Road over the Mill River bridge replacement project consists of replacing the existing two-span structurally-deficient concrete-arch bridge with a new single span prestressed concrete beam bridge on the same general alignment. The work will extend approximately 300 feet south of the bridge and 200 feet north of the bridge. This approach roadway work will consist of reconstruction of the existing pavement, minor vertical and horizontal alignment improvements, and safety improvements such as proper guardrail transition to the bridge, pavement markings, and signage. The project will be constructed in one phase using a complete roadway closure with detour around the project site.
Location:
  • City of Northampton
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Project Manager: Jocelyn Dewire
    Estimated Total Contract Cost: $1,615,721.00
    Estimated Total Federal Participating Construction Cost: $2,228,003.07
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 05/07/2011 )

    Contracts (4) Progress
    # 31220 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 2 Final
    # 57728 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68909 -- Construction Contract
    Bridge Replacement (N-19-029) (Concrete) - River Road over the Mill River.

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/20/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Status Advertised 05/07/2011
    Project Management
    100% Design 100% Package Received 12/10/2010
    100% Design 100% Package Comments to DE 02/14/2011
    25% Design 25% Package Received 10/19/2007
    25% Design Design Public Hearing 10/21/2008
    75% Design 75% Package Received 02/23/2009
    75% Design 75% Package Comments to DE 05/19/2009
    Final Design PS&E Received 03/18/2011
    Final Design PS&E to FAPRO 05/03/2011
    Consultant Contract Process Scope to DE 01/27/2003
    Consultant Contract Process NTP Issued 05/23/2003
    Consultant Contract Process Workhours Approved 05/13/2003