Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DARTMOUTH- NEW BEDFORD- RESURFACING AND RELATED WORK ON ROUTE I-195
Location:
  • Town of Dartmouth
  • City of New Bedford
  • Resident Engineer: Charles Hodges Jr
    Construction Contract Value: $9,657,444.29
    Construction Bid Price: $8,544,639.15
    Initial Construction Estimate: $6,550,227.25
    District: District 5

    Contracts (1) Progress
    # 37523 -- Construction Contract
    Project consists of resurfacing and related work on Route I-195 in the Town of Dartmouth and the City of New Bedford. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/14/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/26/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/25/2002
    Project Status Advertised 08/28/2004
    Project Management
    75% Design 75% Package Received 06/23/2004
    Final Design PS&E Received 08/13/2004
    Final Design PS&E to FAPRO 08/13/2004