Project Description:
HOLYOKE- BRIDGE REPLACEMENT, H-21-039, ROUTE 202 (BEECH STREET) OVER B&M R.R.
The purpose of this project is to demolish the existing bridge and replace it with a three span superstructure on new precast concrete abutments and piers. The proposed bridge shall maintain the present vertical and horizontal clearance from the railroad track. The bridge alignment shall be improved to safely accommodate weaving traffic entering from Lyman Street. The curb-to-curb width of the proposed bridge shall be 44 feet, and there shall be one 5'-6" sidewalk. The bridge demolition and construction shall be done in two stages with a one-way travel lane available at all times. A traffic management plan is required.
Location:
  • City of Holyoke
  • Resident Engineer: James White
    Construction Contract Value: $4,854,916.62
    Construction Bid Price: $4,069,182.00
    Initial Construction Estimate: $4,273,841.00
    District: District 2

    Contracts (4) Progress
    # 32169 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract B Final
    # 57730 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 59588 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 70936 -- Construction Contract
    Bridge Replacement Br. No. H-21-039 (Steel) Route 202 (NB) (Beech Street) over the B&M Railroad. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/13/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/30/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 01/06/2003
    Project Status Advertised 09/03/2011
    Project Management
    25% Design 25% Package Received 03/19/2010
    25% Design 25% Package Received 09/02/2010
    25% Design 25% Package Comments to DE 10/20/2010
    25% Design 25% Package Comments to DE 10/20/2010
    25% Design Design Public Hearing 01/20/2011
    75% Design 75% Package Received 04/26/2011
    75% Design 75% Package Comments to DE 06/14/2011
    Final Design PS&E Received 08/12/2011
    Final Design PS&E to FAPRO 08/31/2011
    Consultant Contract Process Scope to DE 07/08/2008
    Consultant Contract Process NTP Issued 07/16/2009