Project Description:
WRENTHAM- CONSTRUCTION OF ROUTE I-495/ROUTE 1A RAMPS
The Work consists of the resurfacing, widening, and improvements of approximately 0.68 miles of Route 1A (South Street) from south of the signalized intersection at Wrentham Crossing to a point approximately 400 feet north of the signalized intersection with the I-495 Northbound ramps. The Work also includes the construction of a new approximately 0.5-mile-long entrance ramp from Route 1A northbound to I-495 Southbound. The proposed work along Route 1A includes full depth pavement widening, mill and overlay, construction of new 10’ wide hot mix asphalt side paths along both of Route 1A and new cement concrete pedestrian curb ramps. The proposed work also includes two new cement concrete retaining walls along Route 1A underneath the I-495 overpasses to support the new side paths. The existing traffic signals at the intersections of Route 1A/Wrentham Crossing, Route 1A/ Wrentham Village Premium Outlets, Route 1A/I-495 Southbound ramps, and Route 1A/I-495 Northbound ramps will be reconstructed. The proposed work for the new entrance ramp includes embankment placement, full depth construction, and shoulder reconstruction along I-495 Southbound.
Location:
  • Town of Wrentham
  • Construction Begins: Autumn 2024
    Resident Engineer: Sean Darling
    Construction Bid Price: $16,500,299.00
    District: District 5
    Current Status: Rock splitting and Blasting is active and continuing as scheduled every Tuesdays and Thursdays at 11:00 o'clock. Water and drainage utilities being installed at the new Ramp. Electrical conduits being installed along left side of RT 1A. Also utility pole relocation ongoing. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 05/20/2025)
    Additional Info: Rock blasting is scheduled at 11:00 o'clock for every Tuesday and Thursday .. (as of 05/20/2025)

    Contracts (3) Progress
    # 115773 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 127360 -- Construction Contract
    Construction of Route I-495/Route 1A Ramps 22% Complete
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/23/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/04/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/06/2002
    Project Status Advertised 07/27/2024
    Project Management
    100% Design 100% Package Received 03/16/2023
    100% Design 100% Package Comments to DE 05/30/2023
    100% Design 100% Package Received - Resub 1 12/17/2023
    25% Design 25% Package Received 11/09/2016
    25% Design 25% Package Comments to DE 12/12/2016
    25% Design 25% Package Comments to DE 03/16/2021
    25% Design 25% Package Rejected 11/23/2016
    25% Design Design Public Hearing 01/26/2022
    75% Design 75% Package Received 04/27/2022
    75% Design 75% Package Comments to DE 08/02/2022
    Final Design PS&E Received 03/01/2024
    Final Design PS&E Received - Resub 1 04/09/2024
    Final Design PS&E Received - Resub 2 06/19/2024
    Consultant Contract Process NTP Issued 11/28/2018