Project Description:
GARDNER- BRIDGE REPLACEMENT, G-01-017, WINTER STREET & G-01-022, MILL STREET OVER BAKER BROOK
This project involves the replacement of two bridges: Winter Street over Baker Brook and Mill Street over Baker Brook. Work also includes reconstruction of bridge approaches, sidewalk, highway guardrail, pavement markings, loam borrow and seeding, and other incidental work. Both bridges will be closed during construction and detours will be posted.
Location:
  • City of Gardner
  • Resident Engineer: Ryan Davison
    Construction Contract Value: $1,839,208.54
    Construction Bid Price: $1,608,040.80
    Initial Construction Estimate: $1,628,710.00
    District: District 3

    Contracts (4) Progress
    # 30274 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 55859 -- Design -- Hwy Eng Open End
    Work will consist of providing services on an open end basis for various projects which require Chapter 253 Dam Safety Permit Review and Completion. Final
    # 64301 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68531 -- Construction Contract
    2 Bridges - Replacement (G-01-017) (Steel) - Winter Street & Superstructure Replacement (G-01-022) (Steel) - Mill Steet both over the Baker River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/02/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/15/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Status Advertised 04/02/2011
    Project Management
    100% Design 100% Package Received 05/14/2009
    100% Design 100% Package Comments to DE 12/14/2009
    25% Design 25% Package Received 05/22/2006
    25% Design 25% Package Comments to DE 07/19/2006
    25% Design Design Public Hearing 11/09/2006
    75% Design 75% Package Received 12/28/2007
    75% Design 75% Package Comments to DE 03/28/2008
    Final Design PS&E Received 06/03/2010
    Final Design PS&E to FAPRO 03/23/2011
    Consultant Contract Process NTP Issued 06/04/2003