Project Description:
HAVERHILL- DRAINAGE IMPROVEMENTS, ROUTE 125 AT FRANZONE DRIVE
The purpose of this project is to replace the existing Corrugated Metal Pipe under Route 125 with Reinforced Concrete Pipe. The work also includes reconstruction of an existing headwall, excavation and removal of the existing corrugated metal pipe culvert system, construction of a new headwall, grass swale, landscaping and other incidental work.
Location:
  • City of Haverhill
  • Resident Engineer: Bernard LaVita
    Construction Contract Value: $287,539.00
    Construction Bid Price: $255,836.00
    Initial Construction Estimate: $203,500.00
    District: District 4
    Current Status: Contract work has been completed. (as of 11/08/2005)

    Contracts (1) Progress
    # 34671 -- Construction Contract
    Drainage Improvement on Franzone Drive at Route 125. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/13/2004
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contract work has been completed.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/24/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/18/2002
    Project Status Advertised 09/20/2003
    Project Management