Project Description: |
HAVERHILL- DRAINAGE IMPROVEMENTS, ROUTE 125 AT FRANZONE DRIVE
The purpose of this project is to replace the existing Corrugated Metal Pipe under Route 125 with Reinforced Concrete Pipe. The work also includes reconstruction of an existing headwall, excavation and removal of the existing corrugated metal pipe culvert system, construction of a new headwall, grass swale, landscaping and other incidental work.
|
Location: |
|
Resident Engineer: | Bernard LaVita |
Construction Contract Value: | $287,539.00 |
Construction Bid Price: | $255,836.00 |
Initial Construction Estimate: | $203,500.00 |
District: | District 4 |
Current Status: | Contract work has been completed. (as of 11/08/2005) |
|