Project Description:
BUCKLAND- CONSTRUCTION OF A PRE-ENGINEERED STEEL STORAGE FACILITY AT MHD MAINTENANCE DEPOT ON ROUTE 2
CONSTRUCTION OF A PRE-ENGINEERED STEEL STORAGE FACILITY AT MHD MAINTENANCE DEPOT ON ROUTE 2
Location:
  • Town of Buckland
  • Resident Engineer: Charles Najimy
    Construction Contract Value: $737,510.00
    Construction Bid Price: $672,975.00
    District: District 1
    Current Status: Site has been paved completely. Loam & seed will be done in the spring. (as of 01/13/2006)

    Contracts (1) Progress
    # 34677 -- Construction Contract
    Construction of a Pre-Engineered Steel Storage Facility. DCAM CATEORY: GENERAL BUILDING CONSTR. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/21/2004
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Site has been paved completely. Loam & seed will be done in the spring.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/23/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 03/21/2003
    Project Status Advertised 12/06/2003
    Project Management
    Final Design PS&E Received 08/05/2003
    Final Design PS&E to FAPRO 08/05/2003