| Project Description: |
DISTRICT 3- CLEAN AND PAINT FOUR STEEL BRIDGES: H-09-013, H-09-012, M-11-003, N-03-010
Bridge painting at the locations described in the contract.
|
| Location: |
|
| Resident Engineer: | Lisa Spezzaferro-Pelleti![]() |
| Construction Contract Value: | $930,500.00 |
| Construction Bid Price: | $881,000.00 |
| Initial Construction Estimate: | $646,740.00 |
| District: | District 3 |
| Current Status: | Top coat is complete on Route 109 over the Charles River bridge in Medfield. (as of 12/12/2005) |
|