| Project Description: |
DISTRICT 3- CONSTRUCTION OF SALT SHEDS
DISTRICT 3- CONSTRUCTION OF CHEMICAL SALT SHEDS.
|
| Location: | |
| Resident Engineer: | Anthony Tavalone![]() |
| Construction Contract Value: | $838,781.17 |
| Construction Bid Price: | $794,090.00 |
| Initial Construction Estimate: | $720,670.00 |
| District: | District 3 |
| Current Status: | The fence work has been completed at the Spencer snow & ice depot. The contractor paint[ed] the doors on the Oxford shed. Punch list items remain. (as of 08/14/2008) |
| Additional Info: | Ability to read this project's electronic reports because of differences in MS Office programs (vers. 2007 in the field vs. vers. 2003 in the office) was obtained at a later date. |
|
Bridges |
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||