Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HOLYOKE- SPRINGFIELD- WEST SPRINGFIELD- HIGHWAY THRIE BEAM GUARDRAIL UPGRADES ALONG I-91 MEDIAN
The work consists of replacing the existing guard rail with Thrie Beam guard rail in the medians on various sections of I-91.
Location:
  • City of Holyoke
  • City of Springfield
  • Town of West Springfield
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: John Gendall
    Estimated Total Contract Cost: $432,677.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project