LANESBOROUGH- BRIDGE REPLACEMENT, L-03-024, NARRAGANSETT AVENUE OVER PONTOOSUC LAKE
The proposed project consists of a complete structural investigation and replacement of the exisiting bridge. It is anticipated that one reversible lane will be maintained during stage construction.
Location:
  • Town of Lanesborough
  • Construction Begins: Spring 2017
    Resident Engineer: Charles Najimy
    Construction Bid Price: $5,950,513.15
    District: District 1

    Contracts (5) Progress
    # 31228 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 2 Final
    # 32169 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract B Final
    # 58595 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 60139 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support servives to support the Bridge Preservation/Betterment Program. Final
    # 97840 -- Construction Contract
    Bridge Replacement Br. No. L-03-024 (Pre-Cast Arch) Narragansett Avenue over Pontoosuc Lake. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/24/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/21/2002
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee PRC Denied 04/14/2003
    Project Review Committee Letter 12/27/2005
    Project Review Committee Resubmitted 10/14/2005
    Project Status Advertised 09/17/2016
    Project Management
    100% Design 100% Package Received 08/18/2016
    100% Design 100% Package Comments to DE 08/31/2016
    100% Design 100% Plans Approved 09/01/2016
    25% Design 25% Package Received 01/19/2016
    25% Design 25% Package Comments to DE 02/22/2016
    25% Design 25% Package Comments to DE 03/14/2016
    25% Design Design Public Hearing 04/28/2016
    75% Design 75% Package Received 06/22/2016
    75% Design 75% Package Comments to DE 07/20/2016
    Final Design PS&E Received 09/08/2016
    Final Design PS&E to Peer Reviewer 09/12/2016
    Final Design PS&E to FAPRO 09/12/2016
    Consultant Contract Process Scope to DE 05/01/2014
    Consultant Contract Process NTP Issued 08/21/2014
    Consultant Contract Process Workhours Approved 08/07/2014