Project Description:
WESTFIELD- COLUMBIA GREENWAY RAIL TRAIL CONSTRUCTION (CENTER DOWNTOWN SECTION)
This section of the multi-phase of the Columbia Greenway Rail Trail project is from Main Street north to the Westfield River bridge (W-25-036). The project includes the replacement of 4 bridges (W-25,014, W-25-015, W-25-016, W-25-017) and construction of a new bridge over Main Street.
Location:
  • City of Westfield
  • Construction Begins: Autumn 2019
    Resident Engineer: Thomas Doody
    Construction Bid Price: $7,677,136.00
    District: District 2

    Contracts (2) Progress
    # 108254 -- Construction Contract
    Construction of the Columbia Greenway Rail Trail and Related Work Including 5 Railroad Bridges Completed
    # 59590 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/23/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/04/2002
    Project Review Committee PRC Tabled 12/03/2003
    Project Review Committee PRC Tabled 06/22/2004
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 05/10/2006
    Project Status Advertised 06/22/2019
    Project Management
    100% Design 100% Package Received 01/15/2019
    100% Design 100% Package Comments to DE 02/15/2019
    25% Design 25% Package Received 10/01/2002
    25% Design 25% Package Received 04/28/2006
    25% Design 25% Package Rejected 11/06/2002
    25% Design Design Public Hearing 06/20/2006
    75% Design 75% Package Received 02/05/2009
    75% Design 75% Package Comments to DE 03/18/2009
    75% Design 75% Package Received - Resub 1 04/23/2018
    Final Design PS&E Received 05/20/2019
    Final Design PS&E Received - Resub 1 06/06/2019