Project Description:
AMESBURY- GEORGETOWN- NEWBURY- NEWBURYPORT- SALISBURY- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE I-95
The work consists of resurfacing I-95 from the Rowley /Georgetown line and extends northerly to the New Hampshire line. This project is 13.4 miles long.
Location:
  • Town of Amesbury
  • Town of Georgetown
  • Town of Newbury
  • City of Newburyport
  • Town of Salisbury
  • Resident Engineer: Paul Pascucci
    Construction Bid Price: $6,715,954.00
    Initial Construction Estimate: $6,948,075.00
    District: District 4
    Current Status: This project is complete. Punch list items have been addressed. No further updates will be forthcoming. (as of 02/03/2006)

    Contracts (1) Progress
    # 34466 -- Construction Contract
    Resurfacing and Related Work on a Section of Interstate 95. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/17/2004
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project is complete. Punch list items have been addressed. No further updates will be forthcoming.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/05/2002
    Project Review Committee PRC Approved 04/14/2003
    Project Review Committee Letter 05/19/2003
    Project Status Advertised 09/20/2003
    Project Management