Project Description:
HADLEY- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE 116
Location:
  • Town of Hadley
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Albert Li
    Estimated Total Federal Participating Construction Cost: $1,412,030.00
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 09/25/2004 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/09/2002
    Project Review Committee PRC Approved 04/14/2003
    Project Review Committee Letter 05/19/2003
    Project Status Advertised 09/25/2004
    Project Management
    100% Design 100% Plans Complete 03/30/2004
    Final Design PS&E Received 07/07/2004
    Final Design PS&E to FAPRO 07/07/2004